6
Development
The main development activities during Q2 2015 included
the drilling of 12 development wells, 11 in Oman, 1 in Area
A Egypt and 1 in Abu Sennan. Siba-5 well has been
cancelled due to weak foundation and Siba-6
Well Pad
Construction and Progress completed with Siba-6
Operations.
The table below provides the status of the wells developed in Q2 2015 as well as the carry-over from 2014:
Country
Basin/Area
Well name
No. of
Wells
Cost
Interest
Status at end Q2 2015
Q4 2014 Carry-over wells
Egypt
Abu Sennan
Al-Jahraa-4
1
78.00%
Initial rate 1,373 bopd, 1.1
MMscf/d, production
restricted down to 622 bopd,
0.4 MMscf/d; maximum rate
1,561 bopd, 1,439 MMscf/d
(lifted with nytrogen)
Oman
Karim Small
Fields
Ilham-P14, SMP-103
2
15.00%
Producing
Iraq
Siba
Siba-4
1
60.00%
Initial rate ~6,000 bcpd @
64/64' choke, 28 MMscf/d
after acid job
Q1 2015
Oman
Karim Small
Fields
Ilham-P11/P12/P16/P25/10H2ST,WRDM-
M25H,JDRK-11/17,SMPG-37,WRDM-K18
10
15.00%
JDRK-17 and Ilham-P16
drilling
Iraq
Siba
Siba-5
1
60.00%
Cancelled the drilling (weak
foundation)
Egypt
Abu Sennan
ASA-3
1
78.00%
Initial rate 588 bopd, 0.21
MMscf/d, production
restricted down to 513 bopd,
0.052 MMscf/d; maximum
rate 1,047 bopd, 0.180
MMscf/d;
Q2 2015
Egypt
Area A
Yusr-63
1
In drilling
Oman
Karim Small
Fields
Ilham-P18, WRDM-M29, JDRK-12, GZ-
4,JDR-6H2 ST/7H2-ST,ILH-
P15/P21,WRDM-M30, SMPH-42/45
11
WRDM-M30 drilling
Total wells spud (2015)
24