Development & Exploration

The main development and exploration activity in the year has been

the drilling at the Block 9 (Iraq) concession

where the Company has completed the drilling on two new wells, Faihaa-3 and Faihaa-4, and started the drilling

on a third well, Faihaa-5

. The table below provides the status of the development and exploration wells for the

reporting period:

Country

Basin/Area

Well Name

No. of

Wells

Cost

Interest

Status at end of 2017

2016 Carry-over Wells

Iraq

Block 9

Faihaa-3

1

60%

Production commenced on 12

February 2017, current production

has stabilized at a rate of

approximately 2,650 bbls (Gross) on

a 40/64” choke size as of year-end.

Oman

Karim Small

Fields

WRDM-K29

1

15%

Producing.

2017

Iraq

Block 9

Faihaa-4

1

60%

Spud 21 April 2017 with drilling

completed on 9 September.

Production began in early February

2018.

Iraq

Block 9

Faihaa-5

1

60%

Spud 16 November 2017.

Production is expected in Q2 2018.

Egypt

Abu Sennan

Al Jahraa SE-2X

1

53%

Exploration well spud 25 April 2017.

The well has been on production

since 12 July 2017 producing at a

rate of 100 boepd.

Egypt

Abu Sennan

Al Jahraa-9

1

53%

Development well spud 10 June

2017 with the rig released on 20

August 2017 - however tests have

shown the produced liquids to be

100% water.

Egypt

Area A

South Kheir 1X

1

70%

Exploration well spud 11 December

2017.

Oman

Karim Small

Fields

KM-P14/P15/P16/P17/P18/P19,

SMPH-11, GZ-P10, HJ SW-P2/P3,

WRDM-K33, SL-P2/P3, JDRK-

15/17, SMPH-14/30, NSM-P6

18

15%

NSM-P6 on drilling.

Total for 2017

23